The OPS "Pur-Pe" and the "Intermediate OPS-2" have passed their final test trial

On the 25th of July, the specialists from the "Ural Industrial - Ural Polar" Corporation conducted the electrical supply on a temporary scheme of the MPN of Western Siberia to the substation of 110/10 kV the OPS "Pur-Pe" and to the substation of 110/10 kV the "Intermidiate OPS-2" to produce the possibility for the commissioning of oil distillation equipment.

The launch of these facilities will be done in August 2011, according to the plan. All the necessary contracts for the maintenance and operational management of electricity supply facilities after they will be launched and separated from the MPN of Western Siberia are already signed by the "Ural Industrial - Ural Polar" Corporation.